CONSTRUCTION UPDATES

Updated Construction ESTIMATED Timelines:

PHASE 2

Construction start scheduled for mid to late March 2022. 

Woodhill Phase 1

Woodhill Phase 1

Construction Start to
June 2022

Woodhill Phase 2

Construction Start to
December 2022

Woodhill Phase 3

Construction start scheduled for

early 2023.

Woodhill Phase 4-6

Due diligence in progress, construction start as well coordination of demolition and infrastructure to start January 2023.

Woodhill Station West PROGRESS UPDATE- 3/21/23

WOODHILL STATION WEST’S 2ND FLOOR FRAMING IS COMPLETE. Mechanical, electrical, and plumbing installation have begun.

Photography by: Rodney L. Brown

Latest Progress on Woodhill Station West (PHASE I) - 3/8/23

Recently Completed as of 3/6/23 Work In Progress as of 3/6/23
Site Storm Retention Complete Second Floor Framing
Foundations Complete Third Floor Framing Layout
Basement Floor Slab and Framing Complete Electrical Layout
First Floor Slab and Framing Complete Plumbing Layout
Stair Towers and Elevator Shaft Complete Mechanical Layout

Woodhill Center East has officially started Construction! – 3/3/23

Woodhill Station West has started Construction!

Share by: